Château de la Colline Saint-Eutrope
Work to restore and enhance the Château on Saint-Eutrope hill began in january 2024. Work is currently underway on the 14th century north curtain wall. By lowering the base of the wall more than two metres of elevation have been restored.
The company is currently preparing the restoration ands reassembly wor.
The mason is clearing the inner facings of the curtain wall and preparing the footings. Tests to clean the masonry have been validated dans repointing tests are being adapted using local unscreened sand, closer to the original mortar.